adccommunitymod (AutomationDirect) asked a question.

Productivity task

Created Date: October 01,2015

Created By: Tecon

**** This post has been imported from our legacy forum. Information in this post may be outdated and links contained in the post may no longer work.****

Hi, sorry for my english. I have a question. Is possible in Productivity suit exporting some task. When I did save the project every tasks were encapsulated into the project, but If I want use some task from later project in my new project, I could not. Is there some solution How exporting task from project?


  • adccommunitymod (AutomationDirect)

    Created Date: October 01,2015

    Created by: Szarman

    I do not believe tasks can be saved individually, and imported into another project. It would be a great feature, and I hope that it is one day implemented in a future upgrade. It would be nice because a library of common tasks could be tested individually, and added to any project without worry (as long as hardware was the same).

  • adccommunitymod (AutomationDirect)

    Created Date: October 01,2015

    Created by: OkiePC

    I am new to this software but I did a trial just now that appears to work well.

    Open a 2nd instance of Productivity Suite and you can drag and drop tasks from one to the other. It seems that any tags are automatically created in the 2nd instance. I used a new blank project for the 2nd instance, so there were no "collisions " to worry about. I do not know what might happen if there were colliding tag names or conflicting task names.

    Actually after a closer look, it appears it moved the task when I dragged and dropped it to the new instance. So it was removed from the original project. I suppose better advice would be to copy and paste the task. If you right click on the task in the project explorer tree, there is a Copy menu option, and the standard Windows shortcut keys work also.

    Expand Post
  • adccommunitymod (AutomationDirect)

    Created Date: October 01,2015

    Created by: ADC_CommTeam02

    This method will only work if you are using the same version of software. This will not work if you are trying to copy or drag a task from 1.10 to 2.0 version.

  • adccommunitymod (AutomationDirect)

    Created Date: October 01,2015

    Created by: kewakl

    Eng, please clarify.

    I seem to remember being able to copy to sub/minor versions...

    Eg.

    Can copy from 1.8.0.19 to 1.8.2.1

    Cannot copy from 1.8 to 1.9

  • adccommunitymod (AutomationDirect)

    Created Date: October 01,2015

    Created by: ADC_CommTeam02

    You are correct you can copy from minor changes just not major revisions. Sorry should have clarified that.

  • adccommunitymod (AutomationDirect)

    Created Date: October 01,2015

    Created by: Adisharr

    Couldn't you just open the old program in a newer version and then copy between instances?

  • adccommunitymod (AutomationDirect)

    Created Date: October 01,2015

    Created by: Szarman

    I was thinking more along the lines of if you had 50-100 different tasks spread out over 20-30 different projects it would be nice to have a task library instead of opening each project and copying out the appropriate task. I guess I could make a master project that has all the tasks in one place so I could only have to open it up and copy and paste. A custom library that is in the task management area that I could drag any one I have ever created right up into the run every scan, or every second area would be even better than copy and paste, and hunting down the task. Most the time I just rewrite it unless I was doing something fancy on comm ports, or analog signals.

    Expand Post
  • adccommunitymod (AutomationDirect)

    Created Date: October 01,2015

    Created by: ADC_CommTeam02

    We appreciate your feedback. We will add this to our list of improvements, and begin looking into possibly adding this to the GUI in a future release. Keep the suggestions coming!

  • adccommunitymod (AutomationDirect)

    Created Date: October 10,2015

    Created by: dieselvette

    The copy & paste technique described is a handy feature, but be careful as sometimes the handling of tag names can be a bit "buggy "...especially when pasting into a project that already has tags in it, or when dealing with structures.

    Double-check every rung for correct tags!

  • adccommunitymod (AutomationDirect)

    Created Date: October 12,2015

    Created by: kewakl

    Before pasting into a project, I make it a point to check the last tag address of every datatype( or *expected* datatypes), this way I can check for UNANNOUNCED - NEWLY created tags.

10 of 11